Duke Energy signs swine waste-derived gas deal in North Carolina
US gas and electricity provider Duke Energy said it has finalised a second deal in 2016 to buy captured methane gas derived from swine waste.
The planned project will use the anaerobic digestion process and be located at farms in Kenansville, North Carolina.
The system will use captured methane gas to generate carbon-neutral renewable electricity at two power stations.
Optima KV, a waste-to-energy specialist, will construct a digester at each farm and pipe the captured methane gas to a centralised facility where it will be cleaned to pipeline quality specifications and injected into the natural gas pipeline system.
The Duplin County location for the proposed facility is in the heart of Smithfield Foods' pork operations. Smithfield Foods is a global food company.
The project should be operational by the summer of 2017. The power will be carbon neutral compared to the emissions that would result if the waste was left to decay at current methods.
"We see continued advancement in this technology in North Carolina," said David Fountain, Duke Energy's North Carolina president. "This project has environmental benefits and is cost-effective for our customers."
Under North Carolina's Renewable Energy Portfolio Standard (REPS), Duke Energy companies must meet specific compliance targets for swine and poultry waste. In March, the company announced a project with Carbon Cycle Energy to use swine waste-derived gas at four power plants in North Carolina.
Expanding the utility's renewable energy output, the captured methane will be treated, injected into the pipeline system and used at two Duke Energy plants: H.F. Lee Station Combined Cycle Plant in Wayne County and Sutton Combined Cycle Plant in New Hanover County.
Collaboration
"Optima is excited about this partnership with Duke Energy and North Carolina swine farmers," said Gus Simmons, partner in Optima KV and concept designer.
He added: "Our on-farm digesters will integrate with and support the farmers' existing operations. By centralising the gas processing, we can take advantage of cost efficiencies and provide carbon-neutral fuel for Duke's existing power plants. It's a great benefit for the environment and for the economy."
Under a 15-year term, Optima KV is expected to produce about 80,000 MMBtus of pipeline-quality captured methane a year. Duke Energy should yield about 11,000MW-hours of renewable energy annually – enough to power about 880 homes for a year.
The renewable energy credits (RECs) generated annually by the effort will help satisfy state mandates, Duke Energy said in a statement.
Since Duke Energy has already filed to have the Lee and Sutton plants designated as new renewable energy facilities, amendments to those filings were made with the NCUC to include fuel from the new project.